Loseley Fields Primary School, Godalming – Heating Distribution & Controls Refurbishment

Explore the project
ClientLoseley Fields Primary School, Godalming, Surrey
Duration6 Weeks
Building usePrimary School Education
Project scopeHeating Distribution Refurbishment, Controls & Plantroom Alterations

Loseley Fields Primary School, Godalming, Surrey — refurbishment of the school’s heating system for Learning Partners Academy Trust, replacing the low temperature hot water distribution throughout the building along with radiators, plantroom alterations and new heating controls. Delivered over six weeks.

A distribution project, not a plant project

Most heating refurbishments are concentrated in one room. This one was not.

At Loseley Fields the work was in the distribution: new low temperature hot water pipework throughout the school, and new radiators and control valves across classrooms and teaching areas. The plantroom alterations were carried out to accommodate that new system rather than being the object of the project.

That changes where the difficulty lies. Plant room work is contained — one room, one door, one set of access arrangements. Distribution work follows the pipework, which means it follows the building, into every space the school actually uses.

Phasing around a school in session

The works were phased across classrooms, corridors and plant areas so that teaching could continue. Each area was released, worked through and returned, with safe access maintained across the site throughout.

Comprehensive risk assessments and method statements were in place for every activity, supported by site inductions and controlled work areas, with coordination with school staff on which spaces were handed over and when.

Scope of works

  • Strip-out and disposal of redundant heating pipework and equipment
  • Installation of new low temperature hot water (LTHW) heating distribution pipework throughout the school
  • Supply and installation of new radiators and associated control valves across classrooms and teaching areas
  • Upgrades and modifications within the existing plantroom to accommodate the new heating system
  • Installation of new heating controls to improve zoning and temperature management
  • Associated electrical works to support plant, pumps and controls
  • Pipework insulation
  • Full system flushing, water treatment and commissioning prior to handover
  • Making good including boxing-in, decoration and full site clean

Making good

On a distribution project the finishing work is not incidental. New pipework runs through occupied classrooms, and the school has to be handed back in a state fit to teach in — boxing-in, decoration and a full site clean formed part of the scope rather than being left for the trust to arrange.

Handover

The system was flushed, water treated, tested and commissioned before handover, and operational documentation was provided on completion.

Whole-building commercial heating distribution work, and the heating controls that govern it, form a substantial part of what ComGas delivers for schools and academy trusts across Surrey.

Comgas Services delivered the heating refurbishment works at Loseley Fields Primary School to a very high standard. The team worked efficiently within a live school environment, ensuring disruption to staff and pupils was kept to an absolute minimum throughout the project.

Communication was clear and proactive from start to finish, and the works were completed safely, on programme and to the quality expected. The upgraded heating system has significantly improved reliability and comfort within the building.

We would have no hesitation in recommending Comgas Services for similar mechanical and heating projects within the education sector.

Capital Projects Lead, Learning Partners Academy Trust
Loseley-fields-primary-school-godalming
Plan your next project

Planning school building-services works?

Talk to ComGas

Looking for a reliable commercial engineering partner?

Current accreditations and registrations.

Gas Safe Registered OFTEC Registered REFCOM F-Gas Certified CHAS Accredited Constructionline Approved
Quick office contact

Prefer WhatsApp?

Message the ComGas office on 01252 214120.

WhatsApp our office