First and Second Fix Bathroom Plumbing
Bathroom plumbing happens in two stages, and getting the sequencing right avoids opening up finished walls or floors later to fix something that should have been caught earlier.
- First fix covers pipework, soil stack and waste routing before walls and floors are closed up
- Second fix covers connecting and commissioning taps, showers, basins and WCs once the room is decorated and tiled
- We carry out the plumbing and heating first and second fix; tiling, fitting the bathroom suite and waterproofing are carried out by others and coordinated around our work
- Correct sequencing avoids reopening finished surfaces to correct a plumbing issue that should have been resolved at first fix