If a building has to keep its heating or hot water while the boiler plant is replaced, a temporary boiler can carry the load until the new plant is commissioned. It works when it is planned as part of the replacement: sized to the load, sited and connected safely, and agreed before the old plant is switched off.
This guide covers when temporary heating is worth arranging, what has to be assessed, and how the changeover is sequenced, using a plant room refurbishment ComGas has delivered.
When you need a temporary boiler
Not every replacement needs one. A school plant room replaced in the summer holidays can often go without, because the heating is not needed while the building is closed. Our guide to replacing a school plant room in the summer holidays sets out that timeline.
Temporary heating earns its place when the building cannot go without heating or hot water for as long as the works take. That usually means:
- sites that stay occupied or operational throughout the works;
- buildings that house vulnerable people, such as care homes;
- replacements that run into the heating season;
- programmes that are longer than the building can manage without heat.
What has to be assessed first
A temporary boiler still has to be the right one for the building. Before we propose anything, we look at:
- The load: the heating or hot water demand the temporary arrangement has to cover.
- Connections: the condition and layout of the existing pipework, connections and isolation points.
- Supplies: whether the gas and electrical supply available suits the likely requirement.
- Siting: where a unit can realistically go, whether inside a plant room, in an external compound or elsewhere on site.
- Access and planning: any constraints on getting the unit in and keeping it there.
That assessment decides what we propose and how quickly it can be arranged. ComGas does not own a hire fleet or have an exclusive arrangement with one hire supplier, so the specification, availability and installation date are confirmed after the site has been assessed, not promised before.
How the changeover works
1. Install and connect the temporary unit
The temporary boiler is positioned and connected into the existing heating or hot water system. Where it runs on gas, connecting it is gas work. Gas Safe Register says that, by law, all gas engineers working in the UK must be Gas Safe registered, and that not every engineer can legally work on every type of gas appliance: the work categories each engineer is qualified for are listed on their Gas Safe ID card. ComGas installs and connects temporary boilers using our Gas Safe registered engineers.
2. Test, purge and check before use
Regulation 22 of the Gas Safety (Installation and Use) Regulations 1998 requires installation pipework to be tested for gastightness immediately after any work that might affect it and, where gas is being supplied, purged. Our guide to gas tightness testing and purging explains the order. After work on a gas appliance, regulation 26(9) requires the engineer to examine the effectiveness of the flue, the supply of combustion air, the operating pressure or heat input, and the appliance’s operation to ensure it functions safely.
3. Isolate the main plant
Once the temporary unit is running, the main plant is isolated so the replacement can start. We hand over the temporary arrangement, confirming what is in place and how it operates.
4. Keep hot water at temperature
If the temporary arrangement supplies hot water, HSE’s guidance on controlling legionella still applies: hot water should be stored at least at 60°C and distributed so that it reaches 50°C (55°C in healthcare premises) within one minute at the outlets.
5. Commission the new plant and remove the temporary unit
When the new plant is back in service, the temporary arrangement is removed and normal operation of the main system is reinstated and confirmed. The removal is coordinated with the rest of the replacement, and the site is left in an agreed, tidy condition.
Example: New Wimbledon Theatre
At New Wimbledon Theatre, ComGas replaced three ageing floor-standing gas boilers with three Hamworthy Purewell commercial boilers and modernised the flues, pipework, pumps, gas-safety systems and controls. A 500 kW temporary boiler installation in the adjacent car park kept the heating running while the permanent plant was isolated, removed and replaced.
The temporary arrangement needed coordinated gas, water, electrical and heating connections, with secure fencing and protection around the external plant. That let the plant room refurbishment go ahead while reducing disruption to the venue’s heating.
What to agree before the old plant goes off
- The load the temporary unit must cover, and whether it serves heating, hot water or both.
- Where it will sit, and how it will be protected and, if it is outside, fenced.
- The gas, water, electrical and heating connections it needs.
- The dates it goes in, the main plant is isolated, and it comes out again.
- How long the arrangement is agreed for. Continuity depends on what has actually been agreed.
Key facts
- A temporary boiler bridges the gap while the main plant is replaced, where the building cannot go without heating or hot water.
- The load, connections, gas and electrical supplies, siting and access are assessed before anything is proposed.
- Gas Safe Register says all gas engineers working in the UK must be Gas Safe registered; the work they are qualified for is listed on their ID card.
- Gas pipework that has been worked on is tested for gastightness and purged, and the appliance is checked, before it is used.
- HSE guidance: store hot water at least at 60°C and distribute it so that it reaches 50°C (55°C in healthcare premises) within one minute.
- At New Wimbledon Theatre, a 500 kW temporary boiler plant in the car park kept the heating running during the plant room refurbishment.
Frequently asked questions
Does ComGas own its hire boilers?
No. We do not operate a hire fleet or have an exclusive arrangement with one hire supplier. We assess the site, specify a suitable arrangement and help organise it. Availability depends on what can be confirmed at the time.
How quickly can a temporary boiler be arranged?
It depends on the specification, what is available at the time, and the connections and access on site. We tell you what is realistic once we have assessed the requirement, rather than promising a timescale in advance.
Can a temporary boiler be connected to our existing system?
Yes. Our Gas Safe registered engineers connect it into the existing heating or hot water system, based on an assessment of your pipework and plant.
Is temporary heating suitable for a care home?
It can be considered for care homes, schools and other occupied buildings, but each site is assessed on its own terms, including any safety, access or continuity needs.